The maintenance dredging of the Mermentau River is coming to a close and the Ingenuity is expected to finish the job approximately a month ahead of schedule. Captain Joe, Chief Mike and Ethan have survived hurricane Harvey and have worked hard to achieve this goal in an injury and incident free manner. Congratulations to the entire crew.

New hose for Ingenuity Inland Dredging
New, 1,350’ float hose behind the Ingenuity

As this project nears completion, management is gearing up for the move to Port Arthur, TX. In the coming weeks the crew and equipment will relocate to the Sabine-Neches Waterway and will be working with the Army Corps of Engineers, Galveston district. As we transition to the new project, it is the goal of the entire crew to continue working towards completing the project efficiently and safely while maintaining Inland’s reputation for quality work.